Project Introduction:

  • Excavation: 1,100,000 m³
  • Embankment: 1,125,000 m³
  • Concrete: 29,000 m³
  • Formwork: 70,000 m²
  • Reinforcement: 1,017 ton

Client: Islamic Republic of Iran Railways

Consultant: Passillo Consulting Engineers

Plan Manager: HARAZ RAH Consulting Engineers Group

Location: Garmsar

Duration: 18 Month

Year: 2008