Qeshm Oil Terminal Project, Offshore Engineering, Procurement and Construction
Crude oil & condensate gas storage project, with capacity of 6,500,000 BBL in South of Qeshm Island.
In this project, crude oil loading & offloading between onshore storage tanks and oil tankers is supposed to be done by on Single Point Mooring (SPM) which is located in 4 Kilometers far from coast line through two 36” pipeline. Transferring capacity is designed to be 9000 m³/h.
This project is includes engineering, procurement and construction of 4.1 km subsea pipe laying, installation of SPM and Pipeline End Manifold (PLEM).
Client: Naft Qeshm Investment Company
PMC: Soroush Energy Pooya Company (SEP)
Location: Qeshm Island (Hormozgan Province)
Duration: 18 Month
Year: 2014