South Pars Gas Development PH19 Onshore Facilities Site Preparation
216 hectare leveling and grading of Phase 19 of South Pars Gas Condensate Field (onshore part) in Tombak zone, east of Kangan in Bushehr province, including engineering, material provision, machine mobilization & excavation, embankment, soil transportation, dynamic compaction, fencing, flood containment and disposal, trenching, construction of site access roads, shore protection system.
Project Introduction:
- Excavation: about 5 million m³.
- Embankment: about 9 million m³.
Client: Petropars (P.P.I)
Location: Kangan
Duration: 15 Month
Year: 2010