Engineering, management and implementation of rail transportation (railways, subways)
Kavir - Garmsar Railway Infrastructure

Kavir - Garmsar Railway Infrastructure

Project Introduction: Excavation: 1,100,000 m³ Embankment: 1,125,000 m³ Concrete: 29,000 m³ Formwork: 70,000 m² Reinforcement: 1,017 ton Client: Islamic Republic of Iran Railways Consultant: Passillo Consulting Engineers Plan Manager: HARAZ RAH Consulting Engineers Group Location: Garmsar Duration: 18 Month Year: 2008

Khoramshahr - Shalamche Railway Infrastructure

Khoramshahr - Shalamche Railway Infrastructure

Project Introduction: Railway line Retrofitting soil by stabilized with lime Client: Gharargah e Khatam al Ambiya Consultant: Metraconsult Engineering Location: Khoramshahr – Shalamche Railway Duration: 6 Month Year: 2007